Some of the Common Defects Occurring in Piling Work are as follows:
- The number of tests stipulated are not carried out.
- Lateral load tests arc not done.
- Sufficient boring data is not kept. At a later date it could not be checked whether boring was upto the required level or not.
- No cross check is done between the quantity of concrete consumed and the theoretical quantity.
- Tilt and shift are not checked before withdrawing casing pipes.
- The steel reinforcement case are not properly fabricated. The pitch of the helical reinforcement is not kept uniform and proper. The length of overlap is not adequate.