Two objects must be kept always in mind while evolving a formwork for ally type of construction:
- The formwork and falsework must be sufficiently strong not to unduly deflect under load.
- The construction must be carried out in a way so as to achieve easy assembly and dismantling, without disturbing the remaining parts and avoiding damage to the concrete.
- The first object can be achieved by adequate design.
- The second object can be achieved making the formwork in panels so that they can be easily dismantled. The following points need attention.
- Panels should wherever possible, be held in place by struts, braces or wedges and should not be nailed together or in position to allow for number of re-uses.
- Folding wedges should he used with braces and struts so that sheeting may be eased away from concrete to avoid sudden stress which may result in damage. These provide correct levels and makes stripping easier.
- Where panels or supports must be nailed in position, care must be taken to ensure that the nail heads are accessible for the stripping operation.
Some parts of the formwork may safely be removed earlier than others. Parts removed may be re-used elsewhere thus reducing the total amount of formwork and falsework. On large works such savings may be considerable and formwork design should be such as to enable part-stripping to be carried out without disturbing the remainder.
Typical details of simple construction for the most common type of work are given in the following paragraphs alongwith sketches. The sketches show timber sheeting only used for the formwork in contact with concrete, but this can be faced with or replaced by plywood or steel panels is desired.
i) Simple Slabs. In case of spans upto 23 metres, joists may be used in single span and carried by ledgers fixed to walls or supported on posts. Holes should be left in walls at suitable intervals so that a wall plate may be bolted to the wall to support the joist. For greater spans or heavier weight of slab intermediate lines of posts and ledger should be used.
ii) Beam and Slab. Stripping order should decide the mode of fabrication and this may take one of three forms:
a) Beam sides, slab sheeting and beam bottom separately and at appropriate intervals. This method is worthwhile when beam sides are required for re-use.
b) Bean sides and slabs sheeting together, and beani bottoms later. This is probably the most common method.
c) All formwork at the same time. The most desirable method when no part of the formwork is required for immediate re-use and when leaving it in position does not interfere with the work.
If part stripping is to be carried out, careful thought must be given to the problem of how this is going to be achieved. Where beam sides are to be stripped before slab sheeting, the latter should be independently supported. Where beam sides and slab sheeting are to be stripped together, sheeting joists can be carried on beam ledgers as shown in Figure. Beams are carried on posts fitted with braced capping pieces. When wooden posts are used, they should be braced to prevent movement or buckling.
Typical Beam and Slab Formwork |
iii) Columns. In case of column formwork, panels should be made by nailing sheeting to yokes or steel panels fixed by bolts as shown in Figure. The two side panels should be the same width as the columns, whist one end panels should be the same plus the twice the sheeting thickness. Yokes on the side panels should project about 15 to 20 on either side of the sheeting whist those on the ends should be the same width as the sheeting. The formwork is held together by bolts passing through the projecting yoke ends and wedges which are driven between the bolts and end pieces.
iv) Walls. Wall forms are generally built up in panels. The two sides are held together by wire ties or bolts and the correct. spacing is ensured by using distance pieces as shown.in Figure. If pieces of wood are used as spaces, they should not be fixed and must. be removed as concrete proceeds. Modern practice is to cat door and window frames into the concrete to save time. Care must be taken to ensure that openings and conduits are accurately, located.
When I saw the Blog postI didn’t expect this much information from this blog due to content shortage but in the end I was the one who scored zero. I want to ask What are the materials required in construction of formwork.
ReplyDeleteSlab formwork
Understanding the constructional details of formwork is crucial for a successful construction project. Formwork plays a vital role in shaping concrete structures. A well-executed construction management plan,
ReplyDeleteensures the formwork is installed correctly, ensuring the structural integrity and safety of the building.