- Prior to testing any exposed length, ensure that suitable provision to anchor the pipes have been made to overcome the end thrust and to prevent involuntary displacement permitted by the flexibility of joints.
- See that sufficient anchorage is provided by filling in with lightly rammed earth around the of each pipe laid in the trench.
- Ensure that sufficient water is available for testing and necessary arrangements made to fill the pipe Line.
- Check that the hydraulic pump and pressure gauges are in proper working order.
- Examine all the joints for leakage under specified pressure. Get the defects, if any, properly rectified. Repeat the test till all the leakages are stopped and line passed by the Engineer-in-Charge. Record this fact with date in the Wore Diary and the Work Passing Register.
- Ensure that, after completion of the testing, trenches are re-filled properly, as specified.
Testing of Pipe Line